File #: 15-1444    Version: Name: Resolution - A Resolution Awarding the Construction Manager At Risk Contract for the Fieldhouse USA and Offsite Infrastructure
Type: Resolution Status: Passed
File created: 7/31/2015 In control: City Council
On agenda: 8/10/2015 Final action: 8/10/2015
Title: Resolution - A Resolution Awarding the Construction Manager At Risk Contract for the Fieldhouse USA and Offsite Infrastructure
Sponsors: Richard Wright, Alan Magee
Attachments: 1. Resolution, 2. Letter from Alan Magee, 3. Summary of Submittals

Title

Resolution - A Resolution Awarding the Construction Manager At Risk Contract for the Fieldhouse USA and Offsite Infrastructure

 

Requested Action

Award Construction Manager at Risk contract for Mansfield Fieldhouse USA and Offsite Infrastructure

 

Recommendation

The Administration recommends that Pete Durant & Associates be awarded the Construction Manager at Risk contract Mansfield Fieldhouse USA and Offsite Infrastructure

 

Description/History

Council has selected the Construction Manager at Risk method as the best value for the construction of Mansfield Fieldhouse USA and Offsite Infrastructure.  The Construction Manager at Risk is responsible for the general construction and the solicitation of subcontractor bids for this project.  As the Construction Manager at Risk, he is required to assist the Architect in developing preliminary cost estimates and construction methods for all projects. His sealed bid submitted to the Architect was based on site locations and construction methods outlined by the Architect and City Staff; and a proposed project cost of $10,620,000.00 for Mansfield Fieldhouse USA and $3,000,000.00 for offsite infrastructure.   No proposed site or construction method has been finalized. Following the Design and Development review, the final site plan and determination of final construction means and methods, a guaranteed maximum price for this project will be presented to Council for their approval.

 

The architect, Magee Architect, solicited competitive sealed proposals for the Construction Manager at Risk, which were opened by the City Secretary on Thursday, July 30, 2015.  A summary of the two (2) proposals submitted is attached.

 

Alan Magee has reviewed all proposals and has recommended that the City award the Construction Manager at Risk contract to Pete Durant & Associates as the best value for the City of Mansfield (see attached Letter).  Also on August 6, 2015 the Mansfield Park Facility Development Corporation approved the authorization to award the Construction Manager at Risk contract to Pete Durant & Associates for the Mansfield Fieldhouse USA project by a vote of 7-0

 

Justification

The Construction Manager at Risk will provide valuable input during the design and construction phase that has successfully saved time and money for the City on past projects

 

Funding Source

Mansfield Fieldhouse USA- MPFDC 1/2 Cent Sales Tax

Offsite Infrastructure- General Fund

 

Attachments

Proposed Resolution

Letter from Alan Magee dated August 3, 2015

Summary of Submittals

 

Prepared By

Richard Wright, Director of Development Services