File #: 23-5611    Version: 1 Name: Resolution – A Resolution of the City Council of the City of Mansfield, Texas, Awarding a Construction Contract to Home Run Construction LLC of Italy, Texas in an Amount Not to Exceed $1,519,130.02 for Construction of a New Parking Lot and Drive at Kather
Type: Resolution Status: Passed
File created: 9/18/2023 In control: City Council
On agenda: 10/9/2023 Final action: 10/9/2023
Title: Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Awarding a Construction Contract to Home Run Construction LLC of Italy, Texas in an Amount Not to Exceed $1,519,130.02 for Construction of a New Parking Lot and Drive at Katherine Rose Memorial Park; Finding That the Meeting at Which This Resolution is Passed is Open to the Public as Required by Law; And Declaring an Effective Date (ARPA, General Obligation Bonds, MPFDC Fund)
Sponsors: Matt Young
Attachments: 1. Resolution, 2. Exhibit A - Bid Tabulation

Title

Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Awarding a Construction Contract to Home Run Construction LLC of Italy, Texas in an Amount Not to Exceed $1,519,130.02 for Construction of a New Parking Lot and Drive at Katherine Rose Memorial Park; Finding That the Meeting at Which This Resolution is Passed is Open to the Public as Required by Law; And Declaring an Effective Date (ARPA, General Obligation Bonds, MPFDC Fund)

 

Requested Action

Consider and Approve a Resolution to Award Construction Contract

 

Recommendation

Approve Resolution

 

Description/History

Katherine Rose Memorial Park, a former pecan orchard named after the wife of the previous land owner, is a 31.29-acre park located at the intersection of Walnut Creek Drive and Smith Street. The park land was purchased in 1992 by the Mansfield Park Facilities Development Corporation (MPFDC) with proceeds from the half cent sales tax. The park was then developed and opened in 1996, in part with grant funding from the Texas Parks and Wildlife Department. Amenities installed over the course of the park’s history have consisted of a children’s playground, picnic pavilions with tables and grills, one large event pavilion with tables and grills, uncovered picnic tables with grills, lighted basketball courts, lighted volleyball courts, horseshoe pits, restroom facilities, circulating trail with exercise stations, a fishing/drainage pond, vehicular access and parking areas, and park equipment such as benches and trash cans.

 

The master plan for these parks was created and produced by Parkhill, Inc. in 2022-23. It has laid out the future development of these parks, addressing needed infrastructure and recreational amenities within the combined 40.72-acre area of parkland. From this plan, the direction and location of Phase 1A has been determined. It includes the realigned pedestrian and vehicular access and parking areas, while maintaining the essence of the original park setting.

 

The project was advertised for bid on August 23rd and 30th. The bid opening was held on September 12th, with five firms submitting bids. Following review of project experience and reference checks, staff is recommending an award to Home Run Construction LLC in the amount of $1,519,130.02. The bid tab is attached. The MPFDC Board of Directors approved the construction contract award at their regular meeting on September 21, 2023.

 

Justification

Existing park amenities require updating, relocation, and renovation due to increased use, flooding events, and for added safety. A master plan of Katherine Rose Memorial Park and Hardy Allmon Soccer Complex was finalized in February 2023. The approval of this construction contract is the next step in the redevelopment/renovation of the park.

 

Funding Source

ARPA, MPFDC 1/2 cent sales tax, General Obligation Bonds

 

Prepared By

Matt Young, Executive Director of Community Services