File #: 23-5691    Version: 1 Name: Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Approving a Change Order with Westra Consultants, LLC for the Design of Drainage Improvements in the Amount of $19,500; Finding that the Meeting at Which this Resolution is Pas
Type: Resolution Status: Passed
File created: 10/27/2023 In control: City Council
On agenda: 11/13/2023 Final action: 11/13/2023
Title: Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Approving a Change Order with Westra Consultants, LLC for the Design of Drainage Improvements in the Amount of $19,500; Finding that the Meeting at Which this Resolution is Passed is Open to the Public as Required by Law; and Declaring an Effective Date (Drainage Utility Fund)
Sponsors: Howard Redfearn
Attachments: 1. Resolution, 2. Exhibit A - Original Agreement, 3. Exhibit B - Feasibility Agreement, 4. Exhibit C - Additional Survey and Flume Design

Title

Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Approving a Change Order with Westra Consultants, LLC for the Design of Drainage Improvements in the Amount of $19,500; Finding that the Meeting at Which this Resolution is Passed is Open to the Public as Required by Law; and Declaring an Effective Date (Drainage Utility Fund)

 

Requested Action

Approve the resolution approving a change order in the amount of $19,500 for engineering design services

 

Description/History

During the June 2022 rain event, several homes in the Red Oak Dr/Willow Creek Dr area flooded. Resolution RE-3951-22 authorized the City to contract with Westra Consultants, LLC for $58,500 to complete analysis of this area and two others. 

 

After the completion of the analysis for this location, recommended alternatives were explored and City staff determined that construction of a new concrete flume was the most cost effective solution. Westra Consultants, LLC was selected to complete a feasibility analysis and develop construction plans for the concrete flume solution for $43,700.

 

Throughout the project the initial scope of the feasibility analysis was expanded to evaluate the impact of the proposed flume on surrounding properties. This was to ensure new flooding would not occur. The expansion of the feasibility scope has resulted in added scope for the construction design portion of this project. This additional scope includes increasing the size of an existing concrete flume and pavement repair in an adjacent street. To accommodate the additional survey and design work needed to complete the project, a change order request for $19,500 has been submitted. Funding for this change order is available from the drainage utility fund.

 

Justification

Survey needs for the properties where the flume would be constructed were included in the original scope. Survey of surrounding properties, and specifically the intersection of Bridge Water Ln and Willow Creek Dr were not included. These were determined to be necessary to ensure those properties would not experience negative impacts because of the proposed improvements. Additional improvements to existing infrastructure will be needed to prevent flooding from the proposed improvements.

 

Funding Source

Drainage Utility Fund

 

Prepared By

Howard Redfearn Environmental Manager, Environmental Services Department