File #: 24-6154    Version: 1 Name: Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Approving an Amendment to the Construction Manager at Risk Contract with Moss Construction for the Harvest Point Public Infrastructure Project for a Guaranteed Maximum Price of
Type: Resolution Status: Passed
File created: 8/16/2024 In control: City Council
On agenda: 8/26/2024 Final action: 8/26/2024
Title: Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Approving an Amendment to the Construction Manager at Risk Contract with Moss Construction for the Harvest Point Public Infrastructure Project for a Guaranteed Maximum Price of $35,971,518.00; Finding that the Meeting at which this Resolution is Passed is Open to the Public as Required by Law; and Declaring an Effective Date (General Fund, TIRZ #4)
Sponsors: Jason Moore
Attachments: 1. Resolution, 2. Revised Cost Proposal Form
Title
Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Approving an Amendment to the Construction Manager at Risk Contract with Moss Construction for the Harvest Point Public Infrastructure Project for a Guaranteed Maximum Price of $35,971,518.00; Finding that the Meeting at which this Resolution is Passed is Open to the Public as Required by Law; and Declaring an Effective Date (General Fund, TIRZ #4)

Requested Action
To consider approving the resolution

Recommendation
It is city staff's recommendation to approve the resolution

Description/History
On April 22, 2024, City Council approved Resolution #4194-24 to authorize the use of the Construction Manager at Risk (CMAR) procurement delivery method for the construction of the Public Infrastructure at Harvest Point, now called the Staybolt Street Public Infrastructure Project.

In this delivery method, the city contracts separately with an engineer, in this case, Dunaway Associates, to deliver the design and engineering for the construction of the public infrastructure, and then contracts with a construction manager during that design phase, to ensure price, schedule, and constructability are managed prior to construction commencing.

The construction manager is responsible for construction performance and commits to delivering the process within a defined schedule and price, either a fixed sum or a guaranteed maximum price (GMP). The construction manager provides construction input to the owner and design engineers during the design phase and operates as the general contractor during the construction phase.

On June 10, 2024, City Council approved resolution number RE-4210-24 awarding the contract to Moss Construction for preconstruction services, and with an amendment for the construction phase GMP to follow. This item reflects that amendment necessary to proceed with construction activities.

Per the scope of services, which includes:
1. Improved and relocation of Lone Star...

Click here for full text