Skip to main content
File #: 16-1926    Version: Name: Resolution - A Resolution Authorizing a Change Order to the Contract with Tiseo Paving Company for the Construction of Paving and Drainage Improvements to East Debbie Lane from Matlock Road to the City Limits Project and Authorizing Additional Funds in th
Type: Resolution Status: Passed
File created: 6/28/2016 In control: City Council
On agenda: 7/11/2016 Final action: 7/11/2016
Title: Resolution - A Resolution Authorizing a Change Order to the Contract with Tiseo Paving Company for the Construction of Paving and Drainage Improvements to the East Debbie Lane from Matlock Road to the City Limits Project and Authorizing Additional Funds in the Amount of $10,250.15 (Street Bond Fund and Utility Bond Fund).
Sponsors: Joe Smolinski, Steve Freeman
Attachments: 1. Resolution
Title
Resolution - A Resolution Authorizing a Change Order to the Contract with Tiseo Paving Company for the Construction of Paving and Drainage Improvements to the East Debbie Lane from Matlock Road to the City Limits Project and Authorizing Additional Funds in the Amount of $10,250.15 (Street Bond Fund and Utility Bond Fund).


Requested Action
Approval of additional fund and the change order to the contract with Tiseo Paving Company and authorizing additional funds.


Recommendation
The Engineering Staff recommends the approval of additional funds and the change order to the contract with Tiseo Paving Company and authorizing additional funds.


Description/History
The project was awarded on August 25, 2014 by Resolution 3031-14 to Tiseo Paving Company for $3,623,731.20. Total funding authorized was $3,804,917.76 which included a 5% contingency.

During the design and construction phases of East Debbie Lane, several adjacent properties were concurrently being developed. Therefore, construction plans that were bid did not incorporate all changes needed to accommodate these developments and several contract quantities had to be increased during the construction of East Debbie Ln.

Item quantity increases include concrete pavement, driveway and curb work and their subsurface components. Additional repair work was also added at the intersection of Debbie Ln and Matlock Rd. Utility overages include 6 additional water line lowerings. Additional paving was also needed at the Community of Hope Church driveway and parking lot to accommodate a shared driveway between the Ladera development and the church.

The requested additional funds are for a construction contract change order in the amount of $10,250.15.

This proposed change order to Tiseo Paving Company will result in a total of 5.28% above the bid amount.


Justification
Unforeseen conflicts caused the quantity increases in both Paving and Utilities. The City Engineer will be in attendance at the ...

Click here for full text