File #: 24-6115    Version: 1 Name: Placeholder for award to CORE for City Hall CMAR
Type: Resolution Status: Passed
File created: 7/16/2024 In control: City Council
On agenda: 8/12/2024 Final action: 8/12/2024
Title: Resolution - A Resolution of the City Council of the City of Mansfield, Texas Approving a Construction Manager at Risk (CMAR) Contract between the City of Mansfield and CORE Construction for Construction Manager at Risk Services Related to the New City Hall Project (the "Project"); Approving Preconstruction Services in an Amount Not to Exceed $45,000.00 Related to the Project; Authorizing the City Manager, or Designee, to Negotiate, Finalize, and Execute the Contract; Finding that the Meeting at which this Resolution is Passed is Open to the Public as Required by Law; and Declaring an Effective Date
Sponsors: Matt Jones
Attachments: 1. Resolution

Title

Resolution - A Resolution of the City Council of the City of Mansfield, Texas Approving a Construction Manager at Risk (CMAR) Contract between the City of Mansfield and CORE Construction for Construction Manager at Risk Services Related to the New City Hall Project (the "Project"); Approving Preconstruction Services in an Amount Not to Exceed $45,000.00 Related to the Project; Authorizing the City Manager, or Designee, to Negotiate, Finalize, and Execute the Contract; Finding that the Meeting at which this Resolution is Passed is Open to the Public as Required by Law; and Declaring an Effective Date

 

Requested Action

Staff is requesting approval of the award of the CMAR contract for City Hall to CORE Construction.

 

Recommendation

Staff recommends approval.

 

Description/History

The current City Hall facility no longer has the capacity to serve the staff who work in the building. Over the past ten years, conference rooms, hallways, and waiting areas have been remodeled to accommodate additional office spaces.

 

In November 2023, the Mansfield City Council and MISD Board met and voted to approved a property exchange where the City of Mansfield received the school district's property along Walnut Creek that includes Geyer Field, administration buildings, original Mansfield High School, historic Rock Gym, and additional developments, and Mansfield ISD received the City Hall facility and additional property behind at 1200 E. Broad St.

 

Justification

This property exchange necessitates a strict timeline for completing the New City Hall Project to facilitate the relocation of MISD staff to the 1200 E. Broad location. The Construction Manager at Risk (CMAR) delivery method improves project schedule management and emphasizes collaboration and problem-solving early in the design process.

 

Funding Source

2024 Certificates of Obligation

 

Prepared By

Matt Jones, Assistant City Manager