Title
Resolution - A Resolution Awarding a Contract Regarding the Sitework for Mansfield Fieldhouse USA Project
Requested Action
Request approval of the resolution for the Sitework for Mansfield Fieldhouse USA Project
Recommendation
Approve resolution for the Sitework for Mansfield Fieldhouse USA project
Description/History
On 6-08-15 City Council determined that the Construction Manager-at-Risk (CMR) method of Construction Contracts would provide the best value for the Sitework for Mansfield Fieldhouse USA project.
On 8-10-15 City Council awarded the CMR Contract to Pete Durant & Associates.
Subcontractor and supplier bids for the construction of the Sitework for Mansfield Fieldhouse USA project were received and opened on October 20, 2015. Based on all the bids received, the Architect and the Construction Manager recommend a Guaranteed Maximum Price of $1,836,012.00 for the Sitework for Mansfield Fieldhouse USA project. Any additional funds needed by the Construction Manager for this project, as outlined in the scope of work indicated on the Contract Documents, will be funded by the Construction Manager.
Justification
Subcontractor and supplier bids for the construction of the Sitework for Mansfield Fieldhouse USA project were received and opened October 20, 2015. Based on all the bids received, the architect and the construction manager recommend a Guaranteed Maximum Price of $1,836,012.00.
Funding Source
Future Bond Proceeds
Prepared By
Richard Wright, Director Development Services