File #: 24-6270    Version: 1 Name: Resolution - A Resolution Awarding Contracts for the Construction of East Broad Street & Wisteria Street Traffic Signal and Intersection Improvements Including McClendon Construction Company, Inc. for Construction, Brittain and Crawford, LLC for Surveying
Type: Resolution Status: Old Business
File created: 10/29/2024 In control: City Council
On agenda: 11/11/2024 Final action:
Title: Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Awarding Contracts for the Construction of East Broad Street & Wisteria Street Traffic Signal and Intersection Improvements Including McClendon Construction Company, Inc. for Construction, Brittain and Crawford, LLC for Surveying, and Raba Kistner, Inc. for Material Testing and Authorizing Funding for an Amount Not to Exceed $1,299,488.90; Finding That the Meeting at Which This Resolution Is Passed Is Open to the Public as Required by Law; And Is Declaring an Effective Date (Street Bond Fund & Street Maintenance Fund)
Sponsors: Raymond Coffman
Attachments: 1. Resolution, 2. Exhibit A, 3. Exhibit B
Title
Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Awarding Contracts for the Construction of East Broad Street & Wisteria Street Traffic Signal and Intersection Improvements Including McClendon Construction Company, Inc. for Construction, Brittain and Crawford, LLC for Surveying, and Raba Kistner, Inc. for Material Testing and Authorizing Funding for an Amount Not to Exceed $1,299,488.90; Finding That the Meeting at Which This Resolution Is Passed Is Open to the Public as Required by Law; And Is Declaring an Effective Date (Street Bond Fund & Street Maintenance Fund)

Requested Action
Consider the Resolution awarding contracts for the Construction of East Broad Street & Wisteria Street Traffic Signal and Intersection Improvements including McClendon Construction Company, Inc. for construction, Brittain and Crawford, LLC for surveying, and Raba Kistner, Inc. for material testing and authorizing funding for an amount not to exceed $1,299,488.90.

Recommendation
The Engineering Staff recommends approval of the Resolution.

Description/History
This project includes construction of a new traffic signal at the intersection of E. Broad and Wisteria St., reconstruction of failed concrete street panels and construction of additional sidewalk along the East side of Wisteria Street from Broad St. south to the Union Pacific Railroad crossing.

These improvements will better facilitate the flow of traffic through the intersection of Broad and Wisteria streets. This project will also improve the street condition on both streets and add sidewalk to improving pedestrian connectivity to the immediate area.

The project was bid on October 18th, 2024, and there was one bidder for the project with a bid of $1,098,692.50 from McClendon Construction Company, Inc. See attached bid tabulation.

The contract time for this project will be one hundred eighty (180) working days or approximately 9 months. The limits for this project are from 70’ W...