Title
Resolution - A Resolution Authorizing Funding for an Amount not to Exceed $860,000 for the Construction of Walnut Creek Utility Stabilization and Award of Contract to DCI Contracting, Inc. (Utility Revenue Bond Fund)
Requested Action
The authorization of funds for an amount not to exceed $860,000. To award a contract to DCI Contracting, Inc. for the Construction of Walnut Creek Utility Stabilization and execute other necessary contracts to complete the project.
Recommendation
The Engineering Staff recommends the authorization of funding and award of a contract to DCI Contracting, Inc. for construction.
Description/History
The project was bid on September 11, 2013 and there were four bidders for the project. The low bidder was DCI Contracting, Inc. Bids ranged from a low bid of $758,191.00 to a high bid of $1,011,343.00. Staff is recommending award of this project to DCI and authorization of funding for the bid amount plus 5% contingency for a total of $796,100.55. The total requested funds are for construction plus contingency and material testing services to be accomplished within a budget of $860,000.
The purpose of this project is to repair and replace two existing sewer lines in the Walnut Creek Country Club golf course near hole-8 and hole-10 of the Oaks course. One location is an exposed 8” line that must be replaced and surface erosion stabilized. The other location is a 39” aerial crossing of Walnut Creek that must be replaced and the surrounding creek channel stabilized. The contract time for this project is one hundred five (105) calendar days or approximately 3.5 months.
Justification
Both locations have been in need of repair for several years and the risk of catastrophic failure has increased to an unacceptable level.
The Public Works Director will be in attendance at the meeting to answer Council’s questions regarding the proposed funding and contracts.
Funding Source
Utility Revenue Bond Fund
Prepared By
Gus Chavarria,...