Title
Resolution - A Resolution Determining the Construction-Manager-At-Risk Delivery Method as Providing the Best Value for the Construction of the Bud Ervin Water Treatment Plant Phase V Expansion
Requested Action
Consider the resolution authorizing the Construction-Manager-At-Risk Delivery Method as Providing the Best Value for the Construction of the Bud Ervin Water Treatment Plant Phase V Expansion.
Recommendation
Staff recommends approval
Description/History
A Contract-at-Risk (CMAR) will be retained to assist the City of Mansfield and Plummer and Associates Inc. with value engineering, equipment procurement, project management, and construction.
Justification
CMAR models cost throughout design and provides a guaranteed maximum price. CMAR collaborates with owner and engineer to provide input on constructability. Construction can begin in phases and can include early equipment procurement.
Funding Source
Utility Operations Fund
Prepared By
Alex Whiteway., Assistant Director, Water Utilities Department