File #: 23-5677    Version: 1 Name: Resolution – A Resolution of the City Council of the City of Mansfield, Texas, Approving the Award of a Construction Manager at Risk (CMAR) Contract with Archer Western Construction, LLC., for the Bud Ervin Water Treatment Plant Phase V Expansion; Finding
Type: Resolution Status: Passed
File created: 10/13/2023 In control: City Council
On agenda: 10/23/2023 Final action: 10/23/2023
Title: Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Approving the Award of a Construction Manager at Risk (CMAR) Contract with Archer Western Construction, LLC., for the Bud Ervin Water Treatment Plant Phase V Expansion (Utility Fund)
Sponsors: Jeff Price
Attachments: 1. Resolution
Title
Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Approving the Award of a Construction Manager at Risk (CMAR) Contract with Archer Western Construction, LLC., for the Bud Ervin Water Treatment Plant Phase V Expansion (Utility Fund)

Requested Action
Consider the award and authorization of funding.

Recommendation
The award of a Construction Manager at Risk (CMAR) Contract with Archer Western Construction, LLC, for pre-construction services on the Bud Ervin Water Treatment Plant Phase V Expansion.

Description/History
The existing treatment capacity of the Bud Ervin Water Treatment Plant is rated for 45 MGD. Operating trends and regulatory requirements indicate additional treatment capacity is needed for the City of Mansfield to meet new growth demands. The Bud Ervin Water Treatment Plant is designed to meet an ultimate capacity of 60 MGD. Membrane technology improvements may allow treatment capacity improvements up to 75 MGD utilizing the existing treatment infrastructure and distribution system.

A Resolution authorizing Plummer Associates to design the Bud Evrin Water Treatment Plant Phase V Expansion was passed on January 23, 2023 (RE-3972-23). The scope of this contract includes the engineering design services to expand the treatment capacity of the Bud Ervin Water Treatment Plant up to 75 million gallons per day (MGD). The scope also includes assistance to evaluate and recommend section of the CMAR.

A Resolution determining the Construction Manager at Risk (CMAR) delivery method to provide best value for the construction of the Bud Evrin Water Treatment Plant Phase V Expansion was passed on January 23, 2023 (RE-3972-23).

A request for proposal to provide CMAR services was issued and advertised on July 10, 2023. The proposals were received September 5, 2023. The City staff and Plummer Associates have evaluated the qualified proposals submitted and are recommending award to Archer Western Construction, LLC.

T...