Title
Update; Phase I Design of Community Park on Matlock Road
Requested Action
Project Update Only
Recommendation
Project Update Only
Description/History
The Mansfield Park Facilities Development Corporation (MPFDC) purchased a 60-acre tract in January, 2004, to serve as a community park and a major trail-head and connection for the continuation of the Walnut Creek Linear Park trail system. The MPFDC allocated funds in the FY2010-2011 budget to begin the design of the new community park. Land Design Partners was selected to complete the Master Plan phase of the project. That phase included data gathering and site research, site analysis and documentation, visioning sessions, benchmarking, program development, concept development, preliminary master plan and concept design, and culminated with the final master plan. The master plan was approved by the MPFDC and City Council in August of 2011. The MPFDC held a work session with Dunaway Associates, lead by Philip Neeley, in October, 2011, to determine the scope of services for phase 1 construction of the new community park on Matlock Road. It was decided that Phase 1 will include a neighborhood park, a nature park, and a section of the green-belt trail with a trail head and terminus. This proposal includes completing design and construction documents for Phase 1.
January - A kick-off meeting with the consultant and city staff from various departments was held on January 12th. Since the meeting the consultant and staff have started collecting the data to begin the process of creating the base map and final program development.
February - Staff delivered the necessary data, including the tree survey and topographic survey, to the consultant for the completion of the base map. The consultant is currently working on the preliminary park design and plans to present it to the Board at the March meeting.
March - The consultant presented the preliminary design documents to staff on February 28th. On ...