Skip to main content
File #: 24-6286    Version: 1 Name: Resolution - Fire 1 CMAR GMP Amendment
Type: Resolution Status: Passed
File created: 11/1/2024 In control: City Council
On agenda: 11/11/2024 Final action: 11/11/2024
Title: Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Approving an Amendment to the Construction Manager at Risk Contract with Crossland Construction Company, Inc for the Construction of Fire Station No. 1 for a Guaranteed Maximum Price of $12,001,199.00; Finding that the Meeting at which this Resolution is Passed is Open to the Public as Required by Law; and Declaring an Effective Date (Certificates of Obligations)
Sponsors: Matt Jones
Attachments: 1. Resolution, 2. Exhibit A

Title

Resolution - A Resolution of the City Council of the City of Mansfield, Texas, Approving an Amendment to the Construction Manager at Risk Contract with Crossland Construction Company, Inc for the Construction of Fire Station No. 1 for a Guaranteed Maximum Price of $12,001,199.00; Finding that the Meeting at which this Resolution is Passed is Open to the Public as Required by Law; and Declaring an Effective Date (Certificates of Obligations)

 

Requested Action

Staff is requesting approval.

 

Recommendation

Staff recommends approval.

 

Description/History

Fire Station No. 1 is currently situated in Historic Downtown Mansfield, just south of Broad Street and off Main Street. This upcoming construction project will create a modern, state-of-the-art facility for the city’s firefighters, while relocating the station to a new location within Historic Downtown. The move will ensure no interruption to emergency services by enabling a seamless transition, and it will free up valuable Main Street property for more suitable uses, such as retail, dining, and entertainment.

 

Council authorized the use of the Construction Manager at Risk Delivery Method on January 8th, 2024 and approved a CMAR contract with Crossland Construction on July 22nd, 2024.

 

Justification

Crossland Construction and Peak Program Value's efforts on the bidding process for this project resulted in an extremely competitive GMP. Staff and Peak Program Value both recommend the approval of this amendment.

 

Funding Source

Certificates of Obligation

 

Prepared By

Kristen Petree, Management Analyst