File #: 18-2605    Version: 1 Name: Resolution - A Resolution to Consider Contract Amendment #2 to the Design Services Contract with Graham and Associates in the amount of $45,840.50 for Additional Design, Engineering and Construction Documents Related to the North Main Street Trail
Type: Resolution Status: Passed
File created: 1/11/2018 In control: City Council
On agenda: 1/22/2018 Final action: 1/22/2018
Title: Resolution - A Resolution to Consider Contract Amendment #2 to the Design Services Contract with Graham and Associates in the amount of $45,840.50 for Additional Design, Engineering and Construction Documents Related to the North Main Street Trail
Sponsors: Shelly Lanners, Matt Young
Attachments: 1. Resolution

Title

Resolution - A Resolution to Consider Contract Amendment #2 to the Design Services Contract with Graham and Associates in the amount of $45,840.50 for Additional Design, Engineering and Construction Documents Related to the North Main Street Trail

 

Requested Action

Approve a Resolution to Execute a Contract Amendment

 

Recommendation

Approve Resolution

 

Description/History

The 2009 Parks, Recreation, Trails and Open Spaces Master Plan included a spine trail phasing and prioritization plan. The on-street connection with Town Park is shown as segment 12 in the spine trail phasing and prioritization plan and was submitted as a Transportation Alternatives Program (TAP) funding request and was approved for funding received through the Texas Department of Transportation (TxDOT) to develop the on-street connection for a hike and bike trail.

 

A design services contract in the amount of $153,000 was awarded by the City Council to Graham and Associates on April 27, 2015 to provide design services and basic coordination with TxDOT. Following the kick-off meeting with TxDOT, it was determined that the process would require additional schematic design work and plan set submittals from the consultant. Contract Amendment #1 was initiated by staff in May 2016 for an additional $21,000 to complete the additional scope of work, bringing the revised design contract total to $174,000.

 

Since that time, Graham and Associates has worked closely with City staff, TxDOT and the Union Pacific Railroad (UPRR) on design elements and plan submittal reviews. The project bidding deadline was moved forward to August 2017, including all approvals from TxDOT and UPRR. The additional work was beyond their contracted scope of work in Amendment #1 and required multiple submittals at 30%, 60%, 90%, 95% and 100% for review.

 

The project was initially advertised and bid to meet the time frame to preserve the TAP funding, yet was rejected due to non-compliant bids. Graham and Associates modified the plans, submitted to TxDOT and UPRR for review, and re-bid the project, thus requiring additional services to re-prepare the plans and specifications. The proposed Contract Amendment #2 in the amount of $45,840.50 captures all the additional work Graham and Associates has done to complete this portion of the work, resulting in a revised design contract total of $219,840.50.

 

 

Justification

With an increased focus on development in the downtown area, this trail will provide improved pedestrian access into Historic Downtown Mansfield and improve quality of life for Mansfield residents.

 

Funding Source

Street Bond Funds

 

Prepared By

Matt Young

Director of Parks and Recreation

matt.young@mansfieldtexas.gov

817-804-5798