File #: 18-2737    Version: 1 Name: Resolution - A Resolution Awarding a Contract for the Construction of Walnut Creek Drive Right Turn Lane Paving and Signal Improvements (Walnut Creek Drive at Pleasant Ridge Drive) to JLB Contracting, LLC and Authorizing Funding for an Amount Not to Exce
Type: Resolution Status: Passed
File created: 5/8/2018 In control: City Council
On agenda: 5/14/2018 Final action: 5/14/2018
Title: Resolution - A Resolution Awarding a Contract for the Construction of Walnut Creek Drive Right Turn Lane Paving and Signal Improvements (Walnut Creek Drive at Pleasant Ridge Drive) to JLB Contracting, LLC and Authorizing Funding for an Amount Not to Exceed $235,000.00 (Street Bond Fund)
Sponsors: Joe Smolinski, Bart VanAmburgh
Attachments: 1. Resolution, 2. Map, 3. Bid Tab

Title

Resolution - A Resolution Awarding a Contract for the Construction of Walnut Creek Drive Right Turn Lane Paving and Signal Improvements (Walnut Creek  Drive at Pleasant Ridge Drive) to JLB Contracting, LLC and Authorizing Funding for an Amount Not to Exceed $235,000.00 (Street Bond Fund)

Requested Action

Consider a Resolution awarding a contract for the construction of Walnut Creek Drive Right Turn Lane Paving and Signal Improvements (Walnut Creek Drive at Pleasant Ridge Drive) to JLB Contracting, LLC and authorizing funding for an amount not to exceed $235,000.00.

Recommendation

The Engineering Staff recommends approval of the Resolution

Description/History

The project was bid on May 1, 2018 and there were 8 bidders for the project. The lowest qualified bidder was JLB contracting, LLC. Bids ranged from low bid of $205,970.96 to a high bid of $266,002.50.

 

The contract time for this project is Forty Five (45) workind days or approximately 2 months. This project includesconstructing a southbound right turn lane on Walnut Creek Drive. at the intersection of Pleasandt Ridge Drive. It also includes a traffic signal modification and sidewalk replacement. 

 

The requested funds are for a construction contract in the amount of $205,970.96, a 5% construction contingency, material testing, survey and other miscellaneous services needed to complete the construction of the project, to be accomplished within a budget not to exceed $235,000.00.

Justification

JLB Contracting, LLC, has successfully completed work in the City of Mansfield in the past. The Engineering Department feels that JLB Contracting LLC, has the necessary staff and equipment to complete a job of this size and scope within the allowed contract time.

 

The Director of Public Works will be in attendance at this meeting to answer Council's questions regarding the proposed contract. A Resolution is attached for Council's consideration.

Funding Source

The funding source will be from the Street Bond Fund.

Prepared By

Gus Chavarria, CIP Project Manager, Engineering Department