File #: 19-3239    Version: 1 Name: Resolution - A Resolution Awarding a Contract for the Construction of 24” Water Line Improvements (Easy Drive & Hanks Drive) to Whitewater Construction, Inc., and Authorizing Funding for an Amount Not to Exceed $730,000.00 (Utility Bond Fund)
Type: Resolution Status: Passed
File created: 8/16/2019 In control: City Council
On agenda: 8/26/2019 Final action: 8/26/2019
Title: Resolution - A Resolution Awarding a Contract for the Construction of 24” Water Line Improvements (Easy Drive & Hanks Drive) to Whitewater Construction, Inc., and Authorizing Funding for an Amount Not to Exceed $730,000.00 (Utility Bond Fund)
Sponsors: Joe Smolinski, Bart VanAmburgh
Attachments: 1. Resolution, 2. Bid Tab, 3. Street Layout B-2 16063-Layout1
Title
Resolution - A Resolution Awarding a Contract for the Construction of 24” Water Line Improvements (Easy Drive & Hanks Drive) to Whitewater Construction, Inc., and Authorizing Funding for an Amount Not to Exceed $730,000.00 (Utility Bond Fund)
Requested Action
Consider the Resolution awarding a contract for the construction of 24” Water Line Improvements to Whitewater Construction, Inc., and authorizing funding for an amount not to exceed $730,000.00.
Recommendation
The Engineering Staff recommends approval of the Resolution.
Description/History
This project is a 24-inch water line that is part of the Water Capital Improvements Plan. This water line will be constructed along Easy Drive west of Fifth Avenue and will supply the new 2.0 MGD elevated storage tank that will begin construction this fall.

The project was bid on July 18, 2019 and there were eight bidders for the project. The lowest qualified bidder was Whitewater Construction, Inc. Bids ranged from a low bid of $639,793.00 to a high bid of $1,184,478.00.

The contract time for this project is eighty (80) working days or approximately 4 months.

The requested funds are for a construction contract in the amount of $671,782.65, a 5% construction contingency, survey, materials testing and other miscellaneous services needed to complete the construction of the project within a budget not to exceed $730,000.00.
Justification
Whitewater Construction, Inc. has constructed many similar large-diameter water line projects in the recent past. Engineering staff discussed the project scope and requirements in detail with the owner of Whitewater Construction. Both Engineering Staff and the project design engineer have checked multiple project references and discussed those projects in detail with the projects’ owners. The Engineering Department feels that Whitewater Construction, Inc. has the necessary staff and equipment to complete a job of this size and scope within the allowed contract time.

Th...

Click here for full text