File #: 22-4762    Version: Name: Resolution - A Resolution Authorizing Funding in an Amount Not to Exceed $153,510 and Approval of a Contract for Design Services with Halff Associates, Inc. for Glen Abbey Drainage Analysis and Improvements (Drainage Fund).
Type: Resolution Status: Passed
File created: 7/1/2022 In control: City Council
On agenda: 7/11/2022 Final action: 7/11/2022
Title: Resolution - A Resolution Authorizing Funding in an Amount Not to Exceed $153,510 and Approval of a Contract for Design Services with Halff Associates, Inc. for Glen Abbey Drainage Analysis and Improvements (Drainage Fund)
Sponsors: Bart VanAmburgh
Attachments: 1. Resolution, 2. Map
Title
Resolution - A Resolution Authorizing Funding in an Amount Not to Exceed $153,510 and Approval of a Contract for Design Services with Halff Associates, Inc. for Glen Abbey Drainage Analysis and Improvements (Drainage Fund)

Requested Action
Consider the authorization of funding and approval of a contract.

Recommendation
The authorization of funding in an amount not to exceed $153,510 and approval of a contract for design services with Halff Associates, Inc. for Glen Abbey Drainage Analysis and Improvements.

Description/History
A significant storm event occurred on June 3, 2022 causing widespread flooding within the Glen Abbey Drive basin. This has resurfaced past efforts to resolve the flooding issues within the basin. An earlier analysis of the drainage conditions along Glen Abbey was initiated to investigate flooding issues due to a significant storm event in 2008. The results of that analysis produced options which were delayed due to unsuccessful easement acquisition for the necessary infrastructure.

The scope of the current project includes verification of the findings from the Glen Abbey Drainage Analysis dated January 2011 and additional modeling efforts to investigate flooding issues on Glen Abbey Court, two options for dealing with flood conditions, construction plans, and bid assistance for the selected solution. The proposed fee is inclusive of all survey needs and document preparation necessary to publicly bid the project. The anticipated timeline from start of project design to bid is ten months.

The requested funds are for analysis and design services with Halff Associates, Inc. in the amount of $153,510 which includes an additional 5% design fee contingency for potential design scope changes and other miscellaneous services needed to prepare the project for public bidding and construction, for a total budget not to exceed $153,510.00.

Justification
Improvements will be necessary to prevent future flood losses along Glen Abbey Dri...

Click here for full text