File #: 23-5145    Version: 1 Name: A Resolution Authorizing A Contract With Plummer Associates Inc. For The Design Of The Bud Ervin Water Treatment Plant Phase V Expansion For An Amount Not To Exceed $3,535,921.00 (Utility Fund).
Type: Resolution Status: Passed
File created: 1/13/2023 In control: City Council
On agenda: 1/23/2023 Final action: 1/23/2023
Title: Resolution - A Resolution Authorizing a Contract with Plummer and Associates, Inc. for the Bud Ervin Water Treatment Plant Phase V Expansion for an Amount Not to Exceed $3,735,921.00 (Utility Fund)
Sponsors: Jeff Price, Alex Whiteway
Attachments: 1. Resolution
Title
Resolution - A Resolution Authorizing a Contract with Plummer and Associates, Inc. for the Bud Ervin Water Treatment Plant Phase V Expansion for an Amount Not to Exceed $3,735,921.00 (Utility Fund)

Requested Action
Consider Approval of the Contract with Plummer and Associates, Inc. for the Bud Ervin Water Treatment Plant Phase V Expansion.

Recommendation
Staff recommends approval of the Contract with Plummer and Associates, Inc. for the Bud Ervin Water Treatment Plant Phase V Expansion.

Description/History
The scope of this contract includes an evaluation of current membrane technologies and suppliers for the replacement of the Bud Ervin Water Treatment Plant’s existing membrane system with considerations to expand the treatment capacity of the Bud Ervin Water Treatment Plant up to 75 million gallons per day (MGD). The scope also includes the design of the mechanical, electrical, instrumentation, structural, architectural, HVAC and civil processes required to increase the treatment and production of drinking water.

A Contract-at-Risk (CMAR) will be retained to assist the City of Mansfield and Plummer and Associates with the value engineering, equipment procurement, project management, and construction.

The requested funds are for design services with Plummer and Associates, Inc. in the amount of $3,735,921.00, which includes a $200,000 for Special Services for potential design scope changes and other miscellaneous services.


Justification
The existing treatment capacity of the Bud Ervin Water Treatment Plant is rated for 45 MGD. Operating trends and regulatory requirements indicate additional treatment capacity is needed for the City of Mansfield to meet new growth demands. The Bud Ervin Water Treatment Plant is designed to meet an ultimate capacity of 60 MGD. Membrane technology improvements may allow treatment capacity improvements up to 75 MGD utilizing the existing treatment infrastructure and distribution system.

The existing Pall mem...

Click here for full text