File #: 18-2607    Version: 1 Name: Resolution - A Resolution to Consider Approving a Construction Contract with Muckleroy & Falls of Fort Worth, Texas in the amount of $2,485,161 for Site Development and Construction of the Parks and Recreation Administration Building
Type: Resolution Status: Passed
File created: 1/11/2018 In control: City Council
On agenda: 1/22/2018 Final action: 1/22/2018
Title: Resolution - A Resolution to Consider Awarding a Construction Contract to Muckleroy & Falls of Fort Worth, Texas in the amount of $2,485,161 for Site Development and Construction of the Parks and Recreation Administration Building
Sponsors: Shelly Lanners, Matt Young
Attachments: 1. Resolution
Title
Resolution - A Resolution to Consider Awarding a Construction Contract to Muckleroy & Falls of Fort Worth, Texas in the amount of $2,485,161 for Site Development and Construction of the Parks and Recreation Administration Building
Requested Action
Approve a Resolution to Execute a Construction Contract
Recommendation
Approve Resolution
Description/History
The project includes the site development and construction of a new administration building that will house the Parks and Recreation and CVB/Tourism administrative staff at the property owned by the Mansfield Park Facilities Development Corporation (MPFDC) on Matlock Road. Extensive planning and facilitation of staff’s present and future needs are accommodated in the new facility. Currently, administrative staff office in the converted volunteer fire station on Smith Street which is located on the four acres slated for redevelopment in historic downtown.

The proposed single story building is designed to provide office space for 20 staff members, and include a community meeting room, two conference rooms, restrooms, break area, work room, storage space, and a parking lot with site development and improvements to Matlock Road. The building is proposed to be wood construction with a rock masonry exterior and metal roof. The site civil work, parking lot ingress and egress, and infrastructure are included as a portion of this contract.

On December 21, 2017, five bids were received and publicly opened. Muckleroy & Falls was selected as the lowest qualified and responsive bidder with a bid in the amount of $2,481,118. The bid tabulation was checked and it was found to have a computation error resulting in the bid being $4,043 higher than shown on the attached bid tabulation sheet. Two of the other bidders also had computation errors in their bids. Muckleroy & Falls remained the lowest qualified bidder after the corrections.

After analyzing the bids, meeting with the apparent low bidder and checking refere...

Click here for full text