File #: 21-4158    Version: 1 Name: Resolution - A Resolution Determining the Construction Manager-at Risk Method as Providing the Best Value for Construction of the McClendon Park Improvements
Type: Resolution Status: Passed
File created: 6/29/2021 In control: City Council
On agenda: 7/12/2021 Final action: 7/12/2021
Title: Resolution - A Resolution Determining the Construction Manager-At-Risk Delivery Method as Providing the Best Value for Construction of the McClendon Park Improvements
Sponsors: Matt Young
Attachments: 1. Resolution

Title

Resolution - A Resolution Determining the Construction Manager-At-Risk Delivery Method as Providing the Best Value for Construction of the McClendon Park Improvements

Requested Action

Consider and Approve Resolution for Delivery Method

Recommendation

Approve Resolution

Description/History

Texas Government Code section 2267.056(a) requires a City to determine a delivery method that provides the best value to the City before advertising for bids from a contractor if using one of the following options: 1) competitive sealed proposals; 2) design/build contract; 3) a construction manager-agent; 4) a construction manager-at-risk; or 5) a job order contract for the minor repair, rehabilitation, or alteration of a facility.

 

Subject to Council approval, staff will seek out Request for Qualifications from companies qualified to perform the construction. The selection and approval of the recommended, qualified construction company will be scheduled for a future Mansfield Park Facilities Development Corporation agenda and a City Council agenda for approval.

Justification

It is important to select the Construction Manager-At-Risk delivery method before the project is advertised for bid. This method provides the greatest opportunity for saving money and time on the project.

Funding Source

N/A

Prepared By

Matt Young, Director of Community Services