File #: 22-4965    Version: 1 Name: Resolution- A Resolution Awarding a Contract for the Construction of the 30-Inch Transmission Main Crossing Highway 287 and Along Lone Star Road to Blue Star Utilities, LLC and Authorizing Funding for an Amount Not to Exceed $3,874,647.88 (Utility Fund)
Type: Resolution Status: Passed
File created: 10/3/2022 In control: City Council
On agenda: 10/10/2022 Final action: 10/10/2022
Title: Resolution- A Resolution Awarding a Contract for the Construction of the 30-Inch Transmission Main Crossing Highway 287 and Along Lone Star Road to Blue Star Utilities, LLC and Authorizing Funding for an Amount Not to Exceed $3,874,647.88 (Utility Fund)
Sponsors: Bart VanAmburgh
Attachments: 1. Resolution, 2. Map, 3. Bid Tabulation
Title
Resolution- A Resolution Awarding a Contract for the Construction of the 30-Inch Transmission Main Crossing Highway 287 and Along Lone Star Road to Blue Star Utilities, LLC and Authorizing Funding for an Amount Not to Exceed $3,874,647.88 (Utility Fund)

Requested Action
Consider the Resolution awarding contracts for the construction of the 30-Inch Transmission Main Crossing Highway 287 and Along Lone Star Road to Blue Star Utilities, LLC and Authorizing Funding for an Amount Not to Exceed $3,874,647.88.

Recommendation
The Engineering Staff recommends approval of the Resolution.

Description/History
This project includes constructing a 30-inch bar-wrapped concrete cylinder water transmission main across Highway 287 and along Lone Star Road.This project is a portion of Project 14 as shown in the Water Master Plan.

The project was bid on September 22, 2022 and there were seven bidders for the project. Bids ranged from a low bid of $3,437,620.80 to a high bid of $5,292,415.00 The lowest and best bidder is Blue Star Utilities, LLC. See the attached bid tabulation.

The project has a substantial completion date of August 1, 2023. To accommodate a request for increased water service to the City's major wholesale water customer, JCSUD, the project is being incentivized for early completion. The maximum incentive will be issued if the project is substantially complete before May 1, 2023 for an amount not to exceed 5% of the contract price. The incentive will be reduced as the August 1 deadline approaches, then liquidated damages will be withheld if the project is not substantially complete by August 1, 2023.

The requested funds are for a construction contract in the amount of $3,781,382.88, which includes a 5% maximum incentive and a 5% construction contingency, $20,000.00 for survey services which includes a 10% contingency and a $50,000.00 contingency for other miscellaneous services needed to complete the construction of the project, for a total budge...